| .. Licensed to the Apache Software Foundation (ASF) under one |
| or more contributor license agreements. See the NOTICE file |
| distributed with this work for additional information |
| regarding copyright ownership. The ASF licenses this file |
| to you under the Apache License, Version 2.0 (the |
| "License"); you may not use this file except in compliance |
| with the License. You may obtain a copy of the License at |
| |
| .. http://www.apache.org/licenses/LICENSE-2.0 |
| |
| .. Unless required by applicable law or agreed to in writing, |
| software distributed under the License is distributed on an |
| "AS IS" BASIS, WITHOUT WARRANTIES OR CONDITIONS OF ANY |
| KIND, either express or implied. See the License for the |
| specific language governing permissions and limitations |
| under the License. |
| |
| |
| Timetables |
| ========== |
| |
| For DAGs with time-based schedules (as opposed to event-driven), the scheduling |
| decisions are driven by its internal "timetable". The timetable also |
| determines the data interval and the logical date of each run created for the DAG. |
| |
| DAGs scheduled with a cron expression or ``timedelta`` object are |
| internally converted to always use a timetable. |
| |
| If a cron expression or ``timedelta`` is sufficient for your use case, you don't need |
| to worry about timetables. But for more complicated scheduling requirements, |
| you may create your own timetable class and pass that to the DAG's ``schedule`` argument instead. |
| |
| Some examples: |
| |
| * Data intervals with "holes" between. (Instead of continuous, as both the cron |
| expression and ``timedelta`` schedules represent.) |
| * Run tasks at different times each day. For example, an astronomer may find it |
| useful to run a task at dawn to process data collected from the previous |
| night-time period. |
| * Schedules not following the Gregorian calendar. For example, create a run for |
| each month in the `Traditional Chinese Calendar`_. This is conceptually |
| similar to the sunset case above, but for a different time scale. |
| * Rolling windows, or overlapping data intervals. For example, one may want to |
| have a run each day, but make each run cover the period of the previous seven |
| days. It is possible to "hack" this with a cron expression, but a custom data |
| interval would be a more natural representation. |
| |
| .. _`Traditional Chinese Calendar`: https://en.wikipedia.org/wiki/Chinese_calendar |
| |
| As such, Airflow allows for custom timetables to be written in plugins and used by |
| DAGs. An example demonstrating a custom timetable can be found in the |
| :doc:`/howto/timetable` how-to guide. |
| |
| Built-in Timetables |
| ------------------- |
| |
| Airflow comes with several common timetables built in to cover the most common use cases. Additional timetables |
| may be available in plugins. |
| |
| .. _CronTriggerTimetable: |
| |
| CronTriggerTimetable |
| ^^^^^^^^^^^^^^^^^^^^ |
| |
| A timetable that accepts a cron expression, and triggers DAG runs according to it. |
| |
| .. seealso:: `Differences between the two cron timetables`_ |
| |
| .. code-block:: python |
| |
| from airflow.timetables.trigger import CronTriggerTimetable |
| |
| |
| @dag( |
| timetable=CronTriggerTimetable('0 1 * * 3', timezone='UTC'), # At 01:00 on Wednesday |
| ) |
| def example_dag(): |
| pass |
| |
| It is also possible to provide a static data interval to the timetable. The optional ``interval`` argument |
| must be a :class:`datetime.timedelta` or ``dateutil.relativedelta.relativedelta``. If given, a triggered DAG |
| run's data interval would span the specified duration, and *ends* with the trigger time. |
| |
| .. code-block:: python |
| |
| from datetime import timedelta |
| |
| from airflow.timetables.trigger import CronTriggerTimetable |
| |
| |
| @dag( |
| # Runs every Friday at 18:00 to cover the work week (9:00 Monday to 18:00 Friday). |
| timetable=CronTriggerTimetable( |
| "0 18 * * 5", |
| timezone="UTC", |
| interval=timedelta(days=4, hours=9), |
| ), |
| ) |
| def example_dag(): |
| pass |
| |
| |
| .. _DeltaDataIntervalTimetable: |
| |
| DeltaDataIntervalTimetable |
| ^^^^^^^^^^^^^^^^^^^^^^^^^^ |
| |
| Schedules data intervals with a time delta. Can be selected by providing a |
| :class:`datetime.timedelta` or ``dateutil.relativedelta.relativedelta`` to the ``schedule`` parameter of a DAG. |
| |
| .. code-block:: python |
| |
| @dag(schedule=datetime.timedelta(minutes=30)) |
| def example_dag(): |
| pass |
| |
| .. _CronDataIntervalTimetable: |
| |
| CronDataIntervalTimetable |
| ^^^^^^^^^^^^^^^^^^^^^^^^^ |
| |
| A timetable that accepts a cron expression, creates data intervals according to the interval between each cron |
| trigger points, and triggers a DAG run at the end of each data interval. |
| |
| .. seealso:: `Differences between the two cron timetables`_ |
| |
| This can be selected by providing a string that is a valid cron expression to the ``schedule`` |
| parameter of a DAG as described in the :doc:`/concepts/dags` documentation. |
| |
| .. code-block:: python |
| |
| @dag(schedule="0 1 * * 3") # At 01:00 on Wednesday. |
| def example_dag(): |
| pass |
| |
| EventsTimetable |
| ^^^^^^^^^^^^^^^ |
| |
| Simply pass a list of ``datetime``\s for the DAG to run after. Useful for timing based on sporting |
| events, planned communication campaigns, and other schedules that are arbitrary and irregular but predictable. |
| |
| The list of events must be finite and of reasonable size as it must be loaded every time the DAG is parsed. Optionally, |
| the ``restrict_to_events`` flag can be used to force manual runs of the DAG to use the time of the most recent (or very |
| first) event for the data interval, otherwise manual runs will run with a ``data_interval_start`` and |
| ``data_interval_end`` equal to the time at which the manual run was begun. You can also name the set of events using the |
| ``description`` parameter, which will be displayed in the Airflow UI. |
| |
| .. code-block:: python |
| |
| from airflow.timetables.events import EventsTimetable |
| |
| |
| @dag( |
| timetable=EventsTimetable( |
| event_dates=[ |
| pendulum.datetime(2022, 4, 5, 8, 27, tz="America/Chicago"), |
| pendulum.datetime(2022, 4, 17, 8, 27, tz="America/Chicago"), |
| pendulum.datetime(2022, 4, 22, 20, 50, tz="America/Chicago"), |
| ], |
| description="My Team's Baseball Games", |
| restrict_to_events=False, |
| ), |
| ) |
| def example_dag(): |
| pass |
| |
| .. _Differences between the two cron timetables: |
| |
| Differences between the two cron timetables |
| ------------------------------------------- |
| |
| There are two timetables `CronTriggerTimetable`_ and `CronDataIntervalTimetable`_ that accepts a cron expression. |
| There are some differences between the two: |
| - `CronTriggerTimetable`_ does not take care of *Data Interval*, while `CronDataIntervalTimetable`_ does. |
| - The time when a DAG run is triggered by `CronTriggerTimetable`_ is more intuitive and more similar to what people |
| expect cron to behave than that of `CronDataIntervalTimetable`_ (when ``catchup`` is ``False``). |
| |
| Whether taking care of *Data Interval* |
| ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ |
| |
| `CronTriggerTimetable`_ *does not* care the idea of *data interval*. It means the value of ``data_interval_start``, |
| ``data_interval_end`` and legacy ``execution_date`` are the same - the time when a DAG run is triggered. |
| |
| On the other hand, `CronDataIntervalTimetable`_ *does* care the idea of *data interval*. It means the value of |
| ``data_interval_start`` and ``data_interval_end`` (and legacy ``execution_date``) are different. They are the start |
| and end of the interval respectively. |
| |
| The time when a DAG run is triggered |
| ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^ |
| |
| There is no difference between the two when ``catchup`` is ``True``. :ref:`dag-catchup` tells you how DAG runs are |
| triggered when ``catchup`` is ``True``. |
| |
| When ``catchup`` is ``False``, there is difference in how a new DAG run is triggered. `CronTriggerTimetable`_ triggers |
| a new DAG run *after* the current time, while `CronDataIntervalTimetable`_ does *before* the current time (assuming |
| the value of ``start_date`` is past time). |
| |
| Here is an example showing how the first DAG run is triggered. Supposes there is a cron expression ``@daily`` or |
| ``0 0 * * *``, which is aimed to run at 12AM every day. If you enable DAGs using the two timetables at 3PM on January |
| 31st, `CronTriggerTimetable`_ will trigger a new DAG run at 12AM on February 1st. `CronDataIntervalTimetable`_, on the other |
| hand, will immediately trigger a new DAG run which is supposed to trigger at 12AM on January 31st if the DAG had been |
| enabled beforehand. |
| |
| This is another example showing the difference in the case of skipping DAG runs. Suppose there are two running DAGs |
| using the two timetables with a cron expression ``@daily`` or ``0 0 * * *``. If you pause the DAGs at 3PM on January |
| 31st and re-enable them at 3PM on February 2nd, `CronTriggerTimetable`_ skips the DAG runs which are supposed to |
| trigger on February 1st and 2nd. The next DAG run will be triggered at 12AM on February 3rd. `CronDataIntervalTimetable`_, |
| on the other hand, skips the DAG runs which are supposed to trigger on February 1st only. A DAG run for February 2nd |
| is immediately triggered after you re-enable the DAG. |
| |
| By these examples, you see how `CronTriggerTimetable`_ triggers DAG runs is more intuitive and more similar to what |