Title: Fluo Project Incubation Status

This page tracks the project status, incubator-wise. For more general project status, look on the project website.

Fluo is a distributed system for incrementally processing large data sets stored in Accumulo.

The Fluo project graduated on 2017-07-19

  • 2016-05-17 Project enters incubation.

  • 2016-08-07 build-resources-1.0.0-incubating released

  • 2016-08-07 fluo-parent-1-incubating released

  • 2016-10-05 fluo-1.0.0-incubating released

  • 2016-10-27 fluo-recipes-1.0.0-incubating released

  • 2017-05-31 New committer: Christopher McTague

  • 2017-06-12 fluo-1.1.0-incubating released

  • 2017-06-22 fluo-recipes-1.1.0-incubating released

  • link to the main website: https://fluo.apache.org

  • link to the page(s) that tell how to participate (Website,Mailing lists,Bug tracking,Source code): How To Contribute and Get Involved

  • link to the project status file (Committers,non-incubation action items,project resources, etc): Contributors

If the project website and code repository are not yet setup, use the following table:

itemtypereference
Websitewwwhttp://fluo.incubator.apache.org/
Mailing listsdevdev @ fluo.incubator.apache.org
.notificationsnotifications @ fluo.incubator.apache.org
.commitscommits @ fluo.incubator.apache.org
Bug trackingGithub Issueshttps://github.com/apache/incubator-fluo/issues
Bug trackingGithub Issueshttps://github.com/apache/incubator-fluo-recipes/issues
Bug trackingGithub Issueshttps://github.com/apache/incubator-fluo-website/issues
Source codeGIThttps://gitbox.apache.org/repos/asf/incubator-fluo.git
Source codeGIThttps://gitbox.apache.org/repos/asf/incubator-fluo-recipes.git
Source codeGIThttps://gitbox.apache.org/repos/asf/incubator-fluo-website.git
MentorsbillieBillie Rinaldi
.drewDrew Farris
.elserjJosh Elser
CommitterscjnoletCorey Nolet
.ctubbsiiChristopher Tubbs
.elserjJosh Elser
.kturnerKeith Turner
.mwalchMike Walch
.cjmctagueChristopher McTague
Extra..

Project Setup

This is the first phase on incubation, needed to start the project at Apache.

Item assignment is shown by the Apache id. Completed tasks are shown by the completion date (YYYY-MM-dd).

Identify the project to be incubated

dateitem
2016-09-20Make sure that the requested project name does not already exist. Please follow the guide to ensure a suitable project/product name.
2016-06-21If request from anywhere to become a stand-alone PMC, then assess the fit with the ASF, and create the lists and modules under the incubator address/module names if accepted.

Infrastructure

dateitem
2016-05-17Ask infrastructure to set up and archive mailing lists.
2016-06-21Ask infrastructure to create source repository modules and grant the committers karma.
2016-06-21Ask infrastructure to set up issue tracker (JIRA, Bugzilla).
2016-06-21Migrate the project to our infrastructure.

Mentor-related responsibility/oversight

dateitem
2016-06-21Subscribe all Mentors on the pmc and general lists.
2016-06-21Give all Mentors access to the incubator SVN repository. (to be done by the Incubator PMC chair or an Incubator PMC Member wih karma for the authorizations file)
2016-06-21Tell Mentors to track progress in the file ‘incubator/projects/{project.name}.xml’

Copyright

dateitem
2016-05-17Check and make sure that the papers that transfer rights to the ASF been received. It is only necessary to transfer rights for the package, the core code, and any new code produced by the project.
2017-06-22Check and make sure that the files that have been donated have been updated to reflect the new ASF copyright.

Verify distribution rights

dateitem
2017-06-22Check and make sure that for all code included with the distribution that is not under the Apache license, we have the right to combine with Apache-licensed code and redistribute.
2017-06-22Check and make sure that all source code distributed by the project is covered by one or more of the following approved licenses: Apache, BSD, Artistic, MIT/X, MIT/W3C, MPL 1.1, or something with essentially the same terms.

Establish a list of active committers

dateitem
2016-05-17Check that all active committers have submitted a contributors agreement.
2016-05-17Add all active committers in the relevant section above.
2016-05-17Ask root for the creation of committers' accounts in LDAP.

Project specific

Add project specific tasks here.

Incubation

These action items have to be checked for during the whole incubation process.

These items are not to be signed as done during incubation, as they may change during incubation. They are to be looked into and described in the status reports and completed in the request for incubation signoff.

Collaborative Development

  • Have all of the active long-term volunteers been identified and acknowledged as committers on the project?

  • Are there three or more independent committers? (The legal definition of independent is long and boring, but basically it means that there is no binding relationship between the individuals, such as a shared employer, that is capable of overriding their free will as individuals, directly or indirectly.)

  • Are project decisions being made in public by the committers?

  • Are the decision-making guidelines published and agreed to by all of the committers?

Licensing awareness

  • Are all licensing, trademark, credit issues being taken care of and acknowleged by all committers?

Project Specific

Add project specific tasks here.

Exit

Things to check for before voting the project out.

Organizational acceptance of responsibility for the project

  • If graduating to an existing PMC, has the PMC voted to accept it?

  • If graduating to a new PMC, has the board voted to accept it?

Incubator sign-off

  • Has the Incubator decided that the project has accomplished all of the above tasks?